COMMON EXCAVATION TO SPOILEXCAVATION IN SWAMPEXISTING SWAMP CONDITIONS BEFORE WORKSFILL IN SWAMPLAYING OF GEOTEXTILEROCKFILL
Previous
Next

PROJECT DESCRIPTION:

The project was over 14km from Pallisa towards Kumi inclusive of 2.9km of Swamps and several rock outcrops. There are three major townships of Pallisa, Akadot, Kibaale, Kamuge-Olinga, Mukongoro and Kanyum with proximity to schools and local markets. Borrow pits were within 2.5km radius of the road.

PROJECT DETAILS:

  • Category: Road Works
  • Client: Arab Contractors for UNRA
  • Location: Pallisa, Uganda
  • Date: June 2018 to March 2020
  • Duration: 21 Months
  • Project Value: UGX 7.86bn. (Circa $2.2m)
  • Personnel: Circa 50
  • Status: Completed

PROJECT SCOPE:

  • 200,000m3 of fill,
  • 60,000m3 of cut,
  • 33HA of clear and grub,
  • 32,000m3 of topsoil removal,
  • 50,000m3 of swamp excavations,
  • 5,000m3 of Rockfill,
  • 60,000m2 of Geotextile,
  • 54,000m3 of common excavation,
  • 33,000m3 of subgrade G15 material,
  • 7,000m3 of excavation in Rock.