PROJECT DESCRIPTION:
The project was over 14km from Pallisa towards Kumi inclusive of 2.9km of Swamps and several rock outcrops. There are three major townships of Pallisa, Akadot, Kibaale, Kamuge-Olinga, Mukongoro and Kanyum with proximity to schools and local markets. Borrow pits were within 2.5km radius of the road.
PROJECT DETAILS:
- Category: Road Works
- Client: Arab Contractors for UNRA
- Location: Pallisa, Uganda
- Date: June 2018 to March 2020
- Duration: 21 Months
- Project Value: UGX 7.86bn. (Circa $2.2m)
- Personnel: Circa 50
- Status: Completed
PROJECT SCOPE:
- 200,000m3 of fill,
- 60,000m3 of cut,
- 33HA of clear and grub,
- 32,000m3 of topsoil removal,
- 50,000m3 of swamp excavations,
- 5,000m3 of Rockfill,
- 60,000m2 of Geotextile,
- 54,000m3 of common excavation,
- 33,000m3 of subgrade G15 material,
- 7,000m3 of excavation in Rock.